How Long Does a Building Permit Take in the GTA? What to Expect Before a 2027 Start

For a complete application, Ontario's Building Code sets a decision deadline of 10 days for a house, 15 for a small building, 20 for a large one and 30 for a complex one. The clock starts only once the application is complete, so design, zoning approvals and corrections add time before and after it.

One team for design, permits and construction

Multi-unit building under construction in the GTA

Kings Valley Homes · Published November 11, 2026 · Facts checked October 23, 2026

How long does Ontario give a city to decide on a building permit?

If you want a renovation, addition or new build to start in spring 2027, the permit is the step homeowners most often underestimate. The review period itself is short on paper. Most of the real timeline sits around it.

Once a complete application is submitted, the chief building official must either issue the permit or refuse it and give all the reasons in writing within a period set by the Ontario Building Code. The period depends on the class of building (O. Reg. 332/12, Division C, Article 1.3.1.3).

Class of buildingDecision period
A house in which no dwelling unit is above another dwelling unit, plus detached structures serving it that are 55 m² or less10 days
Other Part 9 buildings (generally up to three storeys and 600 m² in building area)15 days
Part 3 (large) buildings20 days
Post-disaster buildings and complex buildings30 days

The City of Toronto publishes these as 10, 15, 20 and 30 business days for a house, small, large and complex building (Toronto Building). The Code, not how big the job feels, decides which class applies. A house where one dwelling unit sits above another, such as a basement apartment under the main unit, is not in the 10-day row, so ask your building department which class applies to your project.

Does the permit clock start the day I apply?

No. The period starts the day after you submit an application that meets the Code's completeness requirements, and it does not count Saturdays, holidays or other days the municipal office is closed to the public (Art. 1.3.1.3, Sentences 7 and 8). Those requirements are administrative: the right application form, all required schedules completed and submitted, the required fees paid, and a written declaration that the application includes the plans and documents the municipality requires and that the work will not contravene applicable law.

A complete application still does not guarantee a decision inside the period. If the chief building official finds that required plans or documents are missing, or that the proposed work would contravene applicable law, the official is not required to decide within the period, but must tell you why in writing within two days.

Comments are also common. If the reviewer asks for changes, the time your design team takes to respond is on your side of the clock.

What has to happen before I can apply?

A permit application is the end of the planning stage, not the start. Under the Building Code Act, 1992, a permit is required before construction (s. 8(1)), and the chief building official must issue it unless the work would contravene the Act, the Building Code or other applicable law, the application is incomplete, or fees are unpaid (s. 8(2)). Before you submit, you typically need:

  • Drawings and design decisions. Permit-ready plans take time, and changing the scope after drawings begin usually means redoing them.
  • Zoning compliance. If your design does not meet the zoning by-law, you may need a minor variance from the committee of adjustment first. The Planning Act (s. 45(1)) lets the committee authorize a minor variance where the general intent of the zoning by-law and the official plan is maintained.
  • A designer where the law requires one. A permit can be refused if the Architects Act or the Professional Engineers Act requires an architect or engineer to be responsible for the design and it is not (Building Code Act, s. 8(2)).
  • Other approvals. Approvals under other laws, such as City Planning or Conservation Authority permits, can delay a permit when they are not in place. Markham names them as a common cause of delay, and Richmond Hill's submission checklist includes an Applicable Law Declaration and, where applicable, the Committee of Adjustment decision.

How long design and approvals take depends on the project, so we scope it with you at a free consultation rather than quote a generic number.

How do Toronto, Markham and Richmond Hill compare?

All three cities administer the same provincial Building Code, so the decision periods above are the same. What differs is how you submit and what each city publishes as its own targets. Check each city's page before you plan around a date, because portals and targets change.

  • Toronto: publishes 10, 15, 20 and 30 business days for a house, small, large and complex building, and points applicants to the Building Code Commission if they dispute whether the time frames were met (Toronto Building).
  • Markham: applications are submitted online through ePLAN, and paper applications are no longer accepted. A non-refundable $100 pre-application fee is paid before drawings are uploaded, and staff then pre-screen the submission against Markham's submission standards. Markham says a permit can take anywhere from 10 to 40 days, and lists first-review targets in business days (complete / incomplete application): 10 / 20 for houses and other small projects, 15 / 20 for an accessory apartment, 20 / 40 for large buildings and 30 / 40 for complex buildings. Timelines for complete applications begin when the pre-application review is approved (City of Markham).
  • Richmond Hill: the online process has two steps, pre-screening and a formal application. The formal submission and the full fee must be received within two weeks of the Building Division's confirmation email, or you have to resubmit. The City says it will review applications for completeness and reply within 2 business days, and lists 10, 15, 20 and 30 business days for complete applications for a house, small, large and complex building. Applications that are incomplete or inactive for six months are considered abandoned (Building Permits, Building Permit FAQs).

What if the city misses the deadline?

The Building Code Act provides for the Building Code Commission to resolve disputes about the permit time periods (s. 24), and Toronto points applicants to it, with an application form for permit processing time disputes (City of Toronto form). It is a last resort, and a conversation with the plans examiner usually resolves problems sooner. It is still worth knowing the right exists.

What should I do now if I want to start in spring 2027?

Work backward from your target start date:

  • Decide your scope. Lock it in before drawings are finalized.
  • Find out which approvals apply. Ask early whether zoning relief or other sign-offs are likely, before you finalize the design.
  • Allow for holiday closures. The review period does not count holidays or days the municipal office is closed, so an application submitted in late December can take longer on the calendar than the number of days suggests.
  • Plan for comments. The 10-day period is a deadline for a decision on a complete application, not a promise that the permit is issued. The decision can be a refusal with reasons.
  • Talk to your builder early. Line up scope, drawings and a target start date together. See our guide to booking your 2027 start.

Applying earlier gives you buffer without giving up a start date. At our free consultation, we can look at your property and tell you which approvals are likely to apply. For the basics, see whether your project needs a permit and permit rules for additions by city.

Frequently asked questions

Can I start work before the permit is issued?

Not for work that needs a permit. The Building Code Act requires a permit before construction (s. 8(1)), and contravening the Act is an offence (s. 36). Wait for the permit and confirm with your city's building department.

Does a 10-day review mean I'll have my permit in two weeks?

Not necessarily. Ten days, not counting Saturdays, holidays and days the office is closed, is the Code's deadline for a decision on a complete application for a house. The decision can be a refusal with reasons, and if documents are missing or the work would contravene applicable law the city is not required to decide within the period. The permit is issued once the issues are resolved and the other requirements are met.

Do I need a permit for every renovation?

Whether a permit is required depends on the work. Our guide to reno permits in Ontario explains the common triggers, and your city's building department can confirm for your project.

Are permit timelines the same in every GTA city?

The Code's decision periods are provincial and apply in all three cities. Each city's submission steps and published targets are its own, as the comparison above shows.

Sources

Follow Kings Valley Homes on Google

Add Kings Valley Homes as a preferred source on Google

Talk through your timeline

Book a free consultation: call (647) 278-2494 to talk through your project and timeline, or book a consultation online. See our design, permits and project management service.

Call us or send a message, and we'll talk through your property.