This is a city licensing rule, not legal advice about ending a tenancy. Speak with a lawyer before you serve an N13. Facts were checked against official sources on November 17, 2026.
Converting a house to a duplex, triplex or fourplex in Toronto is often treated as a zoning and building-permit problem. If a tenant already lives in the house, a third process can apply: the Rental Renovation Licence under Municipal Code Chapter 662. Not every conversion needs one.
This guide explains when the licence is required, how it differs from a building permit, what the screening form is for, and when demolition rules apply instead. For the construction path, see our multiplex development page and Can I build a 4-unit multiplex on my Toronto lot?. To talk through a property, book a free initial consultation or call (647) 278-2494.
What is a Rental Renovation Licence?
A Rental Renovation Licence is a City of Toronto licence for landlords who issue an N13 notice to repair or renovate a rental unit that must be vacant. The City's Information for Landlords page says the licence is required even if the tenant intends to return, and that each unit with an N13 needs its own licence.
An N13 is a notice to end a tenancy under subsection 50(1)(c) of the Residential Tenancies Act, 2006, for repairs or renovations that require vacant possession. Eviction orders remain the jurisdiction of the Landlord and Tenant Board. A City licence does not decide whether a landlord has the legal right to evict a tenant.
When does a multiplex conversion trigger the licence?
It triggers the licence when two things are both true: there is a tenant in a rental unit, and the landlord issues an N13 because the work requires vacant possession of that unit. A house-to-multiplex conversion can meet that test if the house is rented and the work cannot be done with the tenant in place.
It does not trigger the licence merely because you are adding units. An empty house, an owner-occupied house, or a conversion that can proceed without vacant possession does not, on the City's wording, require the licence. The question is whether an N13 is being issued, not whether the project is called a multiplex.
If more than one tenanted unit must be vacated, each unit needs its own licence.
When is a licence not required?
The City's landlord page states it directly: "If a landlord can complete repairs or renovations without issuing an N13 notice, a Rental Renovation Licence is not required."
The same page says the by-law does not apply to demolitions. If you are demolishing rental housing, you must follow the City's rental housing demolition and replacement process instead, which is covered below.
Do not treat "no licence" as "no other approvals." You may still need a building permit, trade permits and zoning review. See our home renovations and design, permits and project management pages.
How is this different from a building permit?
They are separate approvals. The City's screening form says a Chapter 662 licence "is separate and distinct from a building permit or change of use permit issued by the Chief Building Official pursuant to the Building Code Act, 1992." The work may not proceed until the licence is issued, and a copy of the issued permit must go in with the licence application.
In practice, the building permit comes first, then the licence application. Chapter 662 requires the owner or operator to apply within seven days of delivering the N13, and not to carry out the work until a valid licence has been issued.
A licence also does not replace obligations under the Residential Tenancies Act, or zoning and building-code compliance.
What is the Rental Renovation Licence screening form?
Toronto Building's Multiplex Conversion guide lists the screening form among the required permit documents. The City says the form is required for all permits related to the repair or renovation of a residential unit, and that it helps determine whether the work also needs a Chapter 662 licence.
Submitting the form is not the same as applying for the licence. The form is part of the permit package. The licence, if required, is a later application with its own documents and fee. For a Toronto conversion, plan on completing the form even if you believe no N13 will be issued.
How do you apply, and what is the timeline?
The City's landlord page sets out the sequence. Before you apply, obtain the necessary building permits and have a qualified person confirm that vacant possession is required. A qualified person must be licensed by the Ontario Association of Architects or Professional Engineers Ontario; in some cases the City may accept another professional approved by the Chief Building Official, for work such as asbestos removal.
Apply within seven days of issuing the N13, with a copy of the building permit and any other required permit, a copy of the N13, the fee, and the qualified-person report. Once the City receives a complete application, it issues a Tenant Information Notice within two business days. The landlord must post that notice on the unit door within five calendar days and send the City a photograph of the posting within 14 days. A 14-day notification period then begins. After that, the landlord and tenant sign a declaration stating whether the tenant intends to return, and the landlord submits the accommodation or compensation documents the by-law requires. When the City is satisfied, it issues the licence, which must be posted at the unit during the work.
A licence is valid for 12 months from the date it is issued. If the work is not finished in that time, the landlord must apply for a new licence. If ownership changes, the licence may be transferred, and the new landlord must notify the City within 14 days.
What does the licence cost, and what payments can apply?
The City publishes a licence application fee of $728.00 per unit, effective January 1, 2026, waived for licensed multi-tenant housing operators. Confirm the current amount on the City page before you apply.
The by-law also sets payments to the tenant, separate from the licence fee. If the tenant chooses to return, the landlord must provide temporary comparable housing at similar rents, or monthly rent-gap payments based on average CMHC market rents for rental units built since 2015. If the tenant chooses not to return, the landlord must pay severance equal to three months of those rent-gap payments before the licence is issued. In both cases, the City requires a moving allowance of $1,500 for a studio or one-bedroom unit, or $2,500 for a unit with two or more bedrooms.
Those figures are the City's published amounts as of November 17, 2026. They are not legal advice, and they do not replace amounts that may also be owed under the Residential Tenancies Act.
What if the work is actually a demolition under City rules?
The licence by-law does not apply to demolitions. The City directs you instead to the rental housing demolition and replacement process under Municipal Code Chapter 667.
The City also warns that demolition is defined broadly. In a rental building with six or more dwelling units, work that changes the layout of rental units, including adding or removing bedrooms, may be considered a demolition even if the building remains, and would not be eligible for a Rental Renovation Licence.
A one-unit house being converted to a fourplex will often sit outside that six-or-more-unit threshold, but you should not guess. Ask Toronto Building which process applies before you serve notice or submit drawings.
What should Toronto homeowners do before they renovate a tenanted house?
- Confirm whether anyone in the building is a tenant, and do not serve an N13 without legal advice.
- Decide, with a qualified designer or engineer, whether the work truly requires vacant possession.
- Complete the screening form with the building permit application for a multiplex conversion.
- If an N13 will be issued, diary the seven-day deadline and gather the permit, the notice and the qualified-person report first.
- Ask the City whether Chapter 667 demolition rules apply instead of, or in addition to, Chapter 662.
- Budget time for the tenant notification period and the accommodation or compensation step, which happens before the licence is issued.
Kings Valley Homes can help with design, permits and construction. We do not give tenancy-law advice, and a licence application is the owner's responsibility unless arranged otherwise in writing.
Frequently asked questions
What is a Rental Renovation Licence in Toronto?
It is a City licence required when a landlord issues an N13 notice so that repairs or renovations can proceed with vacant possession of a rental unit, even if the tenant plans to return. It is issued under Municipal Code Chapter 662 and is separate from a building permit.
Does every multiplex conversion need one?
No. The licence is required only if an N13 is issued because the work needs vacant possession of a tenanted unit. If the work can be completed without an N13, the City says the licence is not required. The screening form is still required with many residential renovation permits.
How soon do I have to apply?
Within seven days of delivering the N13, and not before you have the building permit (or change of use permit) and the qualified-person report. Work on that unit must not proceed until the licence is issued.
How much is the fee?
The City lists $728.00 per unit, effective January 1, 2026, waived for licensed multi-tenant housing operators. Check the Information for Landlords page (https://www.toronto.ca/services-payments/permits-licences-bylaws/renovictions-bylaw-development/information-for-landlords/) for the current fee.
Does the licence apply if I am demolishing the house?
No. The City says the Rental Renovation Licence by-law does not apply to demolitions. Follow the rental housing demolition and replacement process, and ask whether Chapter 667 applies to your building.